Kumasi Airport

Although approval was obtained as far back as 1940, it was not until 1947 that documentation for land acquisition was completed and paid for. However by 1943, Kumasi Airport had been completed. The runway was 1200yds (3600ft) long by 150yds (450ft) wide, middle: 50yds (150ft) consolidated for landing and two flanking widths of 50yds (150ft) each for parking.The Department of Civil Aviation emerged immediately after the war.

The P.W.D constructed a Control Tower, Terminal Building, RFFS station and Staff Quarters which covered an area of 2-3acres. Additionally, a wireless station which took care of all radios was constructed at Dichemso at a cost of £ 1,876.16 (Source: PWD, Kumasi Records).

There were extensive developments in 1958 and 1959 by the Ghana Government on the runway, navigational facilities and human resource to enhance internal airline operations.The installation of runway and taxiway lights and the extension of the main runway to the southern part in the late 1970’s was another major improvement to the Kumasi Airport. Whilst the lights enhanced night flying, the extension of the runway enabled operations of short haul jets like the F28. The building of a new Terminal and the installation of a VOR/DME commissioned on 1st December 1993 completed the modernization process.In 2003 Kumasi was declared an International Airport primarily for regional operations with the full complement of Security, Customs and Immigration staff.

On December 15, 2014, the newly rehabilitated runway installed with Aeronautical Ground Lighting Systems was inaugurated. This paved the way for domestic airlines to commence night operations.

Currently, Master Plan studies for the airport is on-going. Some projects planned in the next phase include the construction of additional parking aprons, extension of the runway and the construction of a new terminal building.